Construction of the 50 Street/Legion Street extension north of 53 Avenue into Festival Park is nearing its final stage.

  • Water, sewer, and stormwater mains have been completed, with surface work well underway.
  • Placement of concrete curb and gutters is nearing completion for the extension of 50 Street/Legion Street, 56 Avenue, and the new Festival Park parking lot.
  • Approximately 95% of the concrete work has been completed.
  • Paving of the roads and parking lot is scheduled for late October.

While the intersection of 50 Street/Legion Street and 53 Avenue will be opened upon completion of paving, the new access to Festival Park will not be available until lighting is complete.